Crane hire software —
CPA or contract lift

The difference between CPA and a contract lift is who carries the risk, and it is worth 25–40% on the price. Quote the wrong one and you are exposed.

Start free trial → See pricing

7-day free trial · No card required · From £9/month

CPA versus contract lift

CPA (Contract Plant Hire): you supply crane and operator. The hirer plans and supervises the lift and carries the risk. Lower rate.

Contract Lift: you plan, supervise and carry the risk. You appoint the Appointed Person. Typically 25–40% more than CPA, and your insurance must cover it.

Never let a client call it a contract lift and pay CPA rates.

Crane day rates

CraneDay rate (operated)
20–30t city crane£480–650
35–50t all terrain£650–900
60–80t all terrain£900–1,300
100t all terrain£1,400–1,900
130–160t£2,000–2,800
200t+£3,200–5,500
Crawler 50–100t£1,100–2,200
Spider crane£350–600
Lorry loader / HIAB£320–480

What gets forgotten

  • Mobilisation and demobilisation — £300–1,200 each way, escorts on big cranes
  • Counterweight transport — a 100t crane needs 2–4 extra wagons at £400–900 each
  • Rigging and derigging — half a day each end over 80t, a full day over 160t
  • Appointed Person on a contract lift — £400–700 per day
  • Slinger / signaller — £220–320 per day, often two needed
  • Lifting gear, ground mats and outrigger pads
  • Standby time when the lift waits on a late delivery

Lift planning

A lift plan is required for every lift under LOLER 1998 and BS 7121. Ground bearing pressure matters — a 100 tonne crane on outriggers exerts 15–25 tonnes per m². Radius governs capacity, not weight alone: a 100 tonne crane may only lift 8 tonnes at 30 metres. Always check the duty chart against the actual radius.

COMMON QUESTIONS

Questions.

Under CPA the hirer plans and supervises the lift and carries the risk — you supply crane and operator. Under a contract lift you plan, supervise and carry the risk, and appoint the Appointed Person. A contract lift is typically 25–40% more expensive and your insurance must cover it.
A 20–30 tonne city crane runs £480–650 per day operated, a 100 tonne all terrain £1,400–1,900, and 200 tonne plus from £3,200. Add mobilisation and demobilisation of £300–1,200 each way, plus counterweight transport on anything over 80 tonnes.